Report on progress on 50M range.
Yes we are making progress even if a little slow and steady. 11th May a working bee was arranged, eight or ten people including a couple of ladies turned up. Work achieved; some painting to the steel support frame, timber support beam at rear fixed in place, support posts to rear beam concreted in, steel cleats welded in place for rafters, rafters in central bay fixed in place. Also some weed trimming to 100M range. Saturday 18th, Dennis and Malcolm P made a start laying 250


Report on progress on 50M range.
Yes we are making progress even if a little slow and steady. 11th May - a working bee was arranged, eight or ten people including a couple of ladies turned up. Work achieved; some painting to the steel support frame, timber support beam at rear fixed in place, support posts to rear beam concreted in, steel cleats welded in place for rafters, rafters in central bay fixed in place. Also some weed trimming to 100M range. Saturday 18th, - Dennis and Malcolm P made a start laying